Can I request just an ESI-ID so the building permit can be issued?
Can I request just an ESI-ID so the building permit can be issued?

Sure, no problem.

Warren Prasek avatar
Written by Warren Prasek
Updated over 2 years ago

Absolutely... simply leave the optional "meter install" date blank when requesting the meter.

  1. It will then appear in your dashboard connections list marked as:

    ESI-ID requested status tag

  2. Once the ESI-ID is issued, we'll email it to you, and the status tag will become:

    ESI-ID issued status tag

  3. Then you can arrange the permit and upload it to UtilityOn via the Documents tab:

  • And finally, click the green "Request service" button on the Temporary meter panel to get the power flowing: